RC - Rounded-Corner Submersible Pump Stations
With Integral Valve Vault

  Sizing & Configurations

The standard RC509 and RC611 factory-built pump station package offers a monolithically cast valve vault, in what is an un-used portion of the pump station.

The innovative shape and structural design allow ample space for the interior valve vault, while increasing workable system volumes and decreasing the depth of the excavation. The integral valve vault saves valuable site space with the smaller footprint vs. the ordinary 2-structure approach, and solves the associated problem of differential structural settlement.

The RC509 & RC611 have standard, stockable structural and mechanical components. The standard product design features fast turnaround time on submittals and production. All pump stations are factory assembled and then disassembled sufficiently for shipping. Field erection and reassembly occur in less than 4-hours.

 
   Advantages


  • Single structure with integral monolithic valve vault means
    less excavation.
  • Smaller footprint for tight-sites.
  • Increased working volume can decrease required
    excavation depth.
  • Standard design means fast submittal turnaround time.
  • Stockable components allow for fast production
  • 3-4 Hour field installation time.
  • 20-years of pump station experience

Chart-Larger Image


  Typical 1-day Installation

 

The RC509 or RC611 pump station with integral valve vault is delivered to your jobsite as scheduled, pre-assembled, pre-tested and ready for installation. In the timeframe of just 4-hours, the pump station can be erected, "plugged-in" to your system piping and backfilled.

       Case Study: RC509 delivered and installed in North Truro, MA

9:30am:
Flat bed trucks arrive with
pump station components.
Contractor has excavation
ready for pump station
installation.



10:15am:
Crane off-loads base section
into excavation, additional
sections are set; approximately
one every 30- minutes.


11:15am:
Crane sets long discharge
pipes and pump guide rails
(shipped loose) into station.
Pump station top section
with integral vault is set.

 

12:00 Noon:
Minor reassembly of
ship loose items are
completed in two hours
and backfill begins

 
 
 

Cross section view-Larger Image
Typical Plan View

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 

 